![]() | Fusion Power Associates 2 Professional Drive, Suite 249 Gaithersburg, MD 20879 phone: (301) 258-0545 fax: (301) 975-9869 e-mail: FusionPwrAssoc@aol.com web: http://fusionpower.org |
The information in this FPN is taken from the 07 January issue of the ITER Newsline. For more details on ITER progress, visit http://www.iter.org/whatsnew/
ITER Business Forum
Registration is open now for the 2019 edition of the ITER Business Forum
(IBF/2019) to be held in Antibes, France from 26 to 28 March. At
IBF/2019, representatives of the ITER Organization, the Domestic
Agencies, and main suppliers will be making presentations on industrial
involvement in the project, procurement opportunities, and main future
calls for tender. In specific thematic sessions, registered delegates
will have the opportunity to meet potential partners or subcontractors
at the French, European or international level. A 1-1 meeting schedule
tool is also available on line for all registered companies. To find out
more about the conference, to register to participate, or to reserve a
stand, please see the IBF/2019 website:
http://www.iterbusinessforum.com/home.aspx?f_lang=en
Toroidal Magnet Progress in Italy
The first superconducting winding pack made in Europe for ITER's
D-shaped toroidal field coils is now ensconced in its 200-tonne
protective case. The first-of-a-kind insertion operation was carried out
successfully at SIMIC, in northern Italy. On the insertion rig at SIMIC,
the 110-tonne winding pack is laid out flat. On either side, the two
halves of the steel coil case—the straight inboard segment and the
D-shaped outboard segment—have been positioned at the same height.
Working within tolerances of 0.2 mm, the insertion tooling slowly brings
the "pieces" together and the winding pack disappears inside the heavy
steel case. This first successful insertion operation is a prelude to
nine others to come, as the European Domestic Agency Fusion for Energy
is procuring ten toroidal field coils from winding packs manufactured by
the ASG consortium (Europe) and structural cases procured by Japan.
SIMIC is the European company that has been selected for final cold
testing, insertion and welding activities. Under the contract with
SIMIC, winding packs shipped from ASG are cold tested at -193 degrees
Celsius (80 K) using a combined cycle of nitrogen and helium. Insertion
into the steel structural case comes next, in an operation requiring
sophisticated laser dimensional control technology and complex tooling
in order to move and fit components weighing hundreds of tonnes with
millimetre-level precision. Finally the interior cover plates will be
attached and welded in compliance with stringent standards. The
thickness of the welds (up to 130 mm) and the fact that welding will
have to be carried out from one side only adds to the challenge of this
final operation. Welding is expected to take from four to six months,
followed by the injection of resin to fill any gaps between the winding
pack and the case. For more, see the full report on the Fusion for
Energy website: http://f4e.europa.eu
Poloidal Magnet Progress in Russia
Specialists of the Sredne-Nevsky Shipyard and the Efremov Institute in
Saint Petersburg have completed the eight double pancake windings
required for poloidal field coil #1. After the vacuum pressure
impregnation of each double pancake, the team will start assembling the
coil. Under the responsibility of the Russian Domestic Agency, the
fabrication of poloidal field coil #1 (PF1)—the smallest of ITER's six
poloidal field coils—is progressing. Eight double pancakes made from
coiled layers of niobium-titanium conductor have come off the
fabrication line and six have undergone vacuum pressure impregnation—the
phase during which epoxy resin hardens the insulation materials wrapped
around each conductor turn and creates a rigid assembly. The impregnated
double pancakes will be stacked and joined electrically to form a final
nine-metre-in diameter magnet coil weighing close to 300 tonnes. Double
pancake winding is a highly precise technical operation that has
required the development of advanced technologies and processes. The
most important technologies for the fabrication of PF1 were developed at
the Efremov Institute (JSC "NIIEFA"), which also designed, manufactured
and tested a large part of the equipment. From the signing of the
Procurement Arrangement with the ITER Organization in 2011, through the
fabrication of poloidal field conductor and the latest milestone—winding
completion—development and manufacturing activities have required eight
years to date. Coil manufacture is underway at the Sredne-Nevsky
Shipyard near Saint Petersburg, where the finalized coil assembly will
leave the plant directly atop a barge for the nearby Neva River. The
completed coil is expected early in 2021.
Central Solenoid Progress in US
US ITER and contractor General Atomics recently achieved a major
milestone in fabricating the ITER central solenoid, completing vacuum
pressure impregnation (VPI) on the first production module. The VPI
process is the penultimate step of fabrication that turns almost 6 km of
carefully wound superconducting conductor into a structurally strong,
electrically insulated electromagnet. 'Completion of VPI is a critical
step in the process and the team worked diligently and with great care
to insure its success,' said John Smith, project manager for General
Atomics. 'The first production unit now looks like a central solenoid
module, and it won't be too much longer before it is complete and begins
to function as one.' The central solenoid, often called the 'heart of
ITER,' is essential for operation, serving to initiate plasma and
generate the necessary current for plasma heating and sustainment. Six
modules will be stacked to form the 1,000-tonne central solenoid, which
will be the largest pulsed superconducting magnet in the world when it
is complete. General Atomics is under contract to US ITER to fabricate
the six modules plus one spare. During vacuum pressure impregnation, the
team evacuates a rigid mold encasing the coil and injects a three-part
epoxy mixture to impregnate the insulation materials wrapped around each
conductor turn, plus the ground insulation around the module itself. The
epoxy provides both electrical insulation and structural support to the
module. In a final fabrication step, piping is added and the assembly
undergoes final testing. Fabrication of the modules began in 2016 at the
General Atomics Magnet Technologies Center in Poway, California. The
manufacturing process takes approximately 22-24 months per module plus
an additional 5-6 months of testing. Five modules are currently in
various stages of production.
First ITER Toroidal Magnet to Arrive This Year
A major milepost is projected for 2019 as the first of ITER's powerful,
high-field magnets is scheduled to arrive from Japan under the
responsibility of Japanese QST, the National Institutes for Quantum and
Radiological Science and Technology. Eleven years after completing the
signatures on documents specifying technical and quality control
requirements for the supply of nine toroidal field coils, the Japanese
Domestic Agency is overseeing the last, spectacular sequences on its
first production unit. The toroidal field coils are the ITER magnets
responsible for confining the plasma inside the vacuum vessel using
high-performance, internally cooled superconductors called CICC
(cable-in-conduit) conductors. Following the completion of the single
largest superconductor procurement in industrial history, fabrication of
the final coils is proceeding in Japan (9 toroidal field coils plus 10
coil structures to be sent to Europe) and Europe (10 toroidal field
coils). Each coil is made up of a superconducting winding pack and
surrounding stainless steel coil case. The toroidal field coils are the
largest and most powerful superconductive magnets ever designed, with a
stored magnetic energy of 41 GJ and a nominal peak field of 11.8 T.
Together they weigh in at over 6,000 tonnes including superstructure,
representing 60 percent of the magnetic array on the machine and over
one-fourth of the Tokamak's total weight. They require 4.57 km of
conductor per coil wound into 134 turns in the central core, or winding
pack, of the magnet. And they have required the longest procurement
lead-time of any ITER component, with six out of seven ITER Members
involved in the production of 500 tonnes of niobium-tin superconducting
strand (100,000 km) required for the toroidal field superconducting
cables. The first winding pack to come off the assembly line in Japan is
currently undergoing final inspection by the industrial consortium of
Mitsubishi Heavy Industries/Mitsubishi Electric Corporation. The final
sequence of testing involved high voltage tests, helium leak tests, and
finally cryogenic tests, during which the winding pack is inserted into
a cryostat (see top photo) and cooled to 80 K (-193 °C) to confirm leak
tightness. With the successful end of cold testing, the winding pack is
now undergoing post-cold-test helium leak tests and high voltage tests
and will soon be ready for assembly with its toroidal field coil case.
Five other winding packs are in various stages of production. The
200-tonne case assemblies are also in series production. After
successful fitting tests early last year, two have been delivered to
Europe for insertion activities and a third will arrive this month;
another completed production unit will remain at MItsubishi for the
assembly of the Japanese coil that is due at ITER in 2019. The fitting
tests are the most delicate stage in the coil case manufacturing
process, demonstrating that sub-assemblies manufactured and welded at
different factory sites can be successfully paired with gap tolerances
as strict as 0.25 to 0.75 mm along 15-metre weld grooves.