\documentclass[12pt,twoside]{report}
\usepackage{aries97}
\usepackage{ariesref}
\usepackage{psfig}
%\usepackage{rotating}
\usepackage{cite}
\usepackage{xspace}

\def\gesim{\mathrel{\vcenter{\hbox{$\buildrel>\over\sim$}}}}
\def\lesim{\mathrel{\vcenter{\hbox{$\buildrel<\over\sim$}}}}
\def\AI{\hbox{ARIES-I}\xspace}
\def\AII{\hbox{ARIES-II}\xspace}
\def\AIII{\hbox{ARIES-III}\xspace}
\def\AIV{\hbox{ARIES-IV}\xspace}
\def\TI{\hbox{TITAN-I}\xspace}
\def\TII{\hbox{TITAN-II}\xspace}
\def\DH{\hbox{D--$^3$He}\xspace}
\def\DD{\hbox{D--D}\xspace}
\def\DT{\hbox{D--T}\xspace}
\def\degC{$^\circ$C\xspace}
\def\SdegC{$\,^\circ$C\xspace}
\def\N{\phantom{-}}
\def\Z{\phantom{0}}
\def\D{\phantom{.0}}
\def\Y{\phantom{$\sim$ }}
\def\X{\times}
\def\HT{\hbox{HT-9}\xspace}

\widowpenalty=10000
\clubpenalty=10000
\begin{document}

\title{\bf 4. SAFETY AND LICENSING }
\author{
\autlist{Don Steiner}{Gayle Cadwallader}{Thomas Dunn}
\autlist{J. Stephen Herring}{Gregory Hofer}{Fred A. Silady}
\autlist{}{Clement P. C. Wong}{}
}
\date{}
\maketitle

\begin{titlepage}
{%baselineskip=1.8ex
\tableofcontents
}
\end{titlepage}

\setcounter{chapter}{3}
\setcounter{page}{1}

\chapter{SAFETY AND LICENSING}

\section{INTRODUCTION}
\label{s-4-1}

During the Assessment Phase the safety and licensing activity focused on four
areas: (1)~a review of Nuclear Regulatory Commission (NRC) documentation as it
relates to jurisdiction, regulation, licensing and tritium requirements in the
context of fusion power systems~\cite{Hof1}; (2)~the evolution of a potential
pathway for development of fusion regulatory policy and
requirements~\cite{Hof2}; (3)~the establishment of top-level safety and
licensing requirements for fusion power systems~\cite{Hof3}; and (4)~the
development of a methodology to demonstrate that sheltering and evacuation is
not required for fusion power systems~\cite{Hof4}.  In addition to the four
activities noted above, several members of the safety and licensing activity
interfaced with, and contributed to, the DOE Fusion Safety Standard Activity.

\section{REVIEW OF NRC DOCUMENTATION}
\label{s-4-2}

The review of NRC documentation was undertaken in order to anticipate the role
that the NRC might have with regard to fusion power systems constructed in the
United States.  The results of our review are reported in four documents
issued by the Project.  The key findings of these documents are summarized in
the following paragraphs.

The first issue investigated was NRC jurisdiction with regard to fusion power
systems~\cite{Hof1}.  In this context the key findings are:

\begin{enumerate}

\item
Fusion processes are included in the NRC scope by virtue of the Atomic
Energy Act of 1954 and subsequent legislation.

\item
It appears that the NRC would have jurisdiction of both Commercial and
Demonstration Fusion Power Systems constructed in the United States.

\end{enumerate}

Given that the NRC might have jurisdiction over fusion power systems, it
seemed prudent to review NRC regulations regarding fission power plants in
order to take advantage of the differences between fusion and fission power.
The key findings of this review~\cite{Hof2} are:

\begin{enumerate}

\item
To anticipate and influence possible NRC regulations of fusion power, one must
be cognizant not only of 10CFR0-199 but also the lower tier documents.

\item
For fusion power plant designers working on structures, systems, and/or
components that are similar or identical to those used in a fission power
plant, a recommended starting point for NRC regulatory criteria is the
Standard Review Plans (NRC \hbox{NUREG-0800}).

\item
For fusion power plant designers working on structures, systems, and/or
components that are unique to a fusion power plant, the Standard Review Plans
may provide guidance for evolving regulatory criteria.

\end{enumerate}

If one assumes that the NRC will be responsible for licensing commercial fusion
power plants, it is important to understand the implications of such an
eventuality.  Therefore, the historical licensing process and the ``one-step''
licensing process used for fission power plants were reviewed.  The key finding
of this review~\cite{Hof3} was that contested hearings can have an enormous
impact on the time-line for licensing and every effort should be made to
resolve issues prior to hearings.

Finally, since tritium will be the most prevalent radio-isotope in a fusion
power plant, NRC requirements with regard to tritium were reviewed~\cite{Hof4}.
It was found that currently, very little tritium is under NRC jurisdiction, and
thus, there is little regulatory record pertaining specifically to tritium.
Therefore, at this time it is not possible to determine what radiological
safeguards and accountability requirements the NRC would impose on tritium
inventories in fusion power plants.  It was also noted that present DOE tritium
accountability requirements do not appear appropriate for fusion power systems.

\section[PATHWAY FOR DEVELOPMENT OF FUSION REGULATION]
{PATHWAY FOR DEVELOPMENT OF FUSION REGULATORY POLICY AND REQUIREMENTS}
\label{s-4-3}

Given that the NRC might have regulatory jurisdiction over fusion power plants
constructed in the U.S., it appeared advisable to lay out a ``strawman''
pathway for developing fusion regulatory policy and requirements.  This
strawman pathway is shown in \hbox{Table~\ref{t-4-3-1}}.

\begin{table}[p]
\caption{}
%\centering{\bf Strawman Pathway For Development Of \\
%Fusion Regulatory Policy and Requirements}
\centering{\bf A Pathway for Development of
Fusion Regulatory Policy \& Requirements}
\vspace{1.0cm}
\renewcommand{\arraystretch}{1.3}
\begin{tabular}{l l @{\hspace{0.5cm}}l }\hline
Time frame & \multicolumn{1}{c}{Action required By}
     & \multicolumn{1}{c}{Proposed action} \\
\hline \\
2 years    & \parbox[t]{1.6truein}{DOE/OFE with fusion community review}
   & \parbox[t]{3.2truein}{Prepare a white paper on fusion characteristics \&
regulation, building on fusion safety standard and assuming NRC to regulate.}\\
\\
1 year     & \parbox[t]{1.6truein}{DOE/OFE and fusion community}
   & \parbox[t]{3.2truein}{Visit NRC commissioners to review white paper, obtain
commissioners views as to fusion regulation \& desired process.}  \\
\\
2 years    & DOE/OFE
   & \parbox[t]{3.2truein}{Address issue of funding for NRC participation in
development of fusion regulations.}\\
\\
1 year     & \parbox[t]{1.6truein}{DOE/OFE and fusion community}
   & \parbox[t]{3.2truein}{Based on above, develop a policy statement to be
presented to the commissioners.} \\
\\
1 year     & DOE/NRC
   & \parbox[t]{3.2truein}{Conduct public meetings to review policy. obtain input,
revise policy \& have DOE/NRC agree to policy.} \\
\\
4 years & DOE/NRC
   & \parbox[t]{3.2truein}{Develop draft fusion CFR requirements based on ITER
experience \& DEMO design \& obtain comments.} \\
\\
4 years & DOE/NRC
   & \parbox[t]{3.2truein}{Develop regulatory guidance on how to meet requirements
\& refine as technology evolves.} \\
\\
\multicolumn{2}{l}{TOTAL:~~15 years} \\
\\ \hline
\end{tabular}
\label{t-4-3-1}
\end{table}


\section{TOP-LEVEL SAFETY REQUIREMENTS}
\label{s-4-4}

The safety and licensing activity developed top-level safety requirements for
fusion power plants.  First, policy statements for the public and for workers
were developed.  These are:

\begin{enumerate}

\item
Operation of the facility shall not disturb the normal, day-to-day activities
of the public.

\item
Operation of the facility shall not expose plant personnel to risks greater
than other power plants.

\end{enumerate}

Next quantitative requirements for radiological, toxic and electromagnetic
exposures were developed.  These requirements are given in
\hbox{Tables~\ref{t-4-4-1}} through \hbox{\ref{t-4-4-3}}.

\vspace{1.cm}

\begin{table}[b]
\caption{}
\centering{\bf Radiological (Dose) Requirements (rem)}
\vspace{1.0cm}
\renewcommand{\arraystretch}{1.3}
\begin{tabular}{l @{\hspace{0.5cm}} c c c }\hline
Description of event     & Off-site level & On-site level \\
\hline \\
Normal \& Anticipated Operational
%\quad\quad Occurrences   & $\sim$0.01/y$^{(a)}$  &  5/$y^{(b)}$ \\
Occurrences   & $\sim$0.01/y$^{(a)}$  &  5/y$^{(b)}$ \\
Off-Normal Conditions and Accidents  & 1/Event$^{(b)}$  & 5/Event$^{(d)}$ \\
\\ \hline
\multicolumn{3}{l}{$^{(a)}$ \parbox[t]{5.8truein}{According to 10CFR50
Appendix~1, Acceptable Annual Dose is in range 0.003 to 0.015~rem depending on
form of effluent and affected organ.}} \\
\multicolumn{3}{l}{$^{(b)}$ \parbox[t]{5.8truein}{To avoid sheltering or
evacuation, dose per event cannot exceed 1~rem~\cite{EPA-520} at site boundary.
}}\\
\multicolumn{3}{l}{$^{(c)}$ Consistent with 10CFR20.} \\
\multicolumn{3}{l}{$^{(d)}$ \parbox[t]{5.8truein}{Consistent with
10CFR835.1302, however, for certain activities (life-saving and protection of
large populations) higher doses are allowed.}} \\
\end{tabular}
\label{t-4-4-1}
\end{table}

\begin{table}[p]
\caption{}
\centering{\bf Toxic Material Requirements}
\vspace{1.0cm}
\renewcommand{\arraystretch} {1.3}
\begin{tabular}{l c c }\hline
\multicolumn{1}{c}{Event}   & Public  & Facility worker \\
\hline \\
\parbox[t]{1.7truein}{Normal \& anticipated operational occurrences}
   & \parbox[t]{2.1truein}{Federal, state, or local regulatory and permit
      requirements}
      & \parbox[t]{2.1truein}{Federal, state, or local regulatory and
        permit requirements}  \\
\\
\parbox[t]{1.7truein}{Off-normal conditions \& accidents per event} & 5 times
   final RQs$^{(a)}$ & 5 times final RQs $^{(a)}$ \\ \\ \hline
\multicolumn{3}{l}{$^{(a)}$ Per 40CFR302.4 and 40CFR355 App.~A (RQ:~Reportable
quantity)}
\end{tabular}
\label{t-4-4-2}
\end{table}

\begin{table}[p]
\caption{}
\centering{\bf Static Electromagnetic Field Exposure Limit for Facility
Workers$^{(a)}$}
\vspace{1.0cm}
\renewcommand{\arraystretch} {1.3}
\begin{tabular}{c @{\hspace{0.8truein}} c @{\hspace{0.8truein}} c}\hline
Magnetic field   & Exposure time      & Body region  \\
\hline \\
\Z0.06~T$^{(b)}$ & continuous 8~h day & trunk       \\
  0.6~T$^{(c)}$  & continuous 8~h day & extremities \\
  2.0~T$^{(d)}$  & short (a few min.) & whole Body  \\
\\ \hline
\multicolumn{3}{l}{$^{(a)}$ \parbox[t]{5.5truein}{Based on evaluation by
Lawrence Livermore National Laboratory in 1987~\cite{Mil87}.  Recommendations
are also available for gradient and time-varying fields, but were judged to be
too detailed for top-level requirements.}} \\
\multicolumn{3}{l}{$^{(b)}$ Maximum average/day in peak fields $>0.5$~T.}  \\
\multicolumn{3}{l}{$^{(c)}$ Maximum average.} \\
\multicolumn{3}{l}{$^{(d)}$ Peak exposure limit.} \\
\end{tabular}
\label{t-4-4-3}
%}\hfil}}
\end{table}

\section{METHODOLOGY FOR SAFETY ANALYSIS}
\label{s-4-5}

A limited hazard assessment was performed on the \AIV design to demonstrate
the methodology for assuring design compliance with the top-level public safety
requirements.  The task also provided insights as to risk-sensitive areas of
the \AIV design.

\begin{figure}[p]
\centerline{\psfig{file=sti-4-5-1.ps,height=7.3truein}}
\caption[f-4-5-1]
{Logic for designing fusion facility to meet Protective Action Guidelines (PAG)
requirement. The goal is to avoid ``risk assessment'' by meeting PAG
requirements by using low-activation material and care in design.}
\label{f-4-5-1}
\end{figure}

Figure~\ref{f-4-5-1} outlines the methodology for evaluating the design against
the top-level safety requirement.  In this case the qualitative safety goal was
for the plant operation to not disturb the normal day-to-day activities of
the public.  This in turn required that the quantitative NRC and Environmental
Protection Agency (EPA) regulations for the normal and accident doses at the
plant boundary be met.  The accident dose is more limiting and specifically a
committed effective dose equivalent of 1~rem corresponds to when sheltering is
first considered~\cite{EPA-520}.  To meet this off-site dose the plant must be
designed to either have insufficient radioactivity that this dose level cannot
be exceeded if it was released to the plant boundary or to show that the
likelihood of this dose being exceeded is negligibly small (smaller than once
in 5 or 10 million plant operation years).  This demonstration can be by
considering the design inherent resistance to radioactivity transport, by
considering the reliability of engineering barriers to release, or by some
combination of inherent and engineered design features.  Initiating events
ranging from anticipated occurrences to rare external events must be considered
as well as events involving multiple independent and dependent failures of both
active and passive structures, systems, and components and operator errors.

The first level evaluation is the hazard risk assessment.  A range of events
for the design are defined and their frequencies estimated.  Best estimate
release fractions of the radiologically important nuclides are determined.  At
this point one can judge whether the Protective Action Guides (PAGs) dose
guidelines may be exceeded for the design and its sources and potential release
mechanisms.  If so, a more detailed evaluation including the uncertainties in
the best estimate releases and doses is performed.  If not, bounding lower
level requirements are set on the structures, systems, and components (SSCs),
{\it e.g.,} the radiological inventory in a given system shall not exceed a
certain value.  Ideally uncertainties on each of the independent variables
(typically 6 to 12 counting all sources and pathways) are assessed.

The overall uncertainty in the dose for a given event is determined by
utilizing a Monte Carlo code to statistically combine uncertainty distribution
of each dependent variable.  Dose distribution for each event can be combined,
weighted by the event frequency to give the overall plant cumulative risk
curve.  It is the cumulative risk curve that once again is now compared to the
PAG requirement.  If the goal is met, lower level risk requirements are set on
the SSCs.  If not, three possibilities remain to show compliance:

\begin{enumerate}

\item
perform a still more detailed evaluation of the event frequencies and
consequences,

\item
specify a research program to show more favorable best estimate results and/or
to narrow the uncertainty on one or more variables, such as the release
fraction,

\item
make design changes that lower the frequency of the high consequence events
and/or lower the consequences of the high frequency events.

\end{enumerate}


If the latter approach of changing the design is chosen another analysis loop
is required to assure that no new high consequence events were introduced.

\subsection{Important Events for ARIES-IV}
\label{s-4-5-1}

Initiating events for existing fission plants, for advanced fission reactor
designs and for fusion designs were reviewed.  Representative events included
primary coolant leaks, loss of off-site power, moisture ingress, and magnet
failures.  Engineering judgment was used to select three potential event
classes thought to be important for the \AIV design to meet the PAG
off-site boundary doses:

\begin{enumerate}

\item
Primary coolant leak in the blanket cooling system;

\item
Primary coolant leak in a purge line;

\item
Moisture ingress into the primary system.

\end{enumerate}

In this limited study only the first class of events was evaluated to
demonstrate the approach and methods and to provide early insights into any
design issues or concerns with compliance to the top-level off-site safety
requirement.  Ultimately the full spectrum of events must be assessed including
those with off-site releases but also those in which a design feature prevents
off-site releases.

\paragraph{Primary coolant leak.}
In the \AIV design the primary coolant is pressurized helium which has safety
advantages (chemically and neutronically inert, single-phase).  The only
serious radioactivity in the helium coolant is due to other gaseous impurities
in it.  However, since it is pressurized it can act as a driving mechanism for
transport of other radioactive sources.  In the selected event, the initiating
event is a failure in the blanket coolant system piping.  This is followed by a
plant shutdown.  In this scenario the helium circulators fail immediately and
are not recovered such that the blanket slowly heats up due to the decay heat
and the loss of forced cooling and helium inventory.

\subsection{Event Frequency Estimate}
\label{s-4-5-2}

For this scoping study a thorough review of leakage data from high pressure
systems with emphasis on nuclear power applications and specifically on
gas-cooled reactors was not undertaken.  Rather an estimate was taken based on
an advanced light water reactor probabilistic risk assessment (PRA).  From the
PRA of Brown Boveri - Combustion Engineering advanced light-water reactor
(ABB-CE~80) small leaks (area less than 0.05~sq.~ft) were assigned a frequency
of 0.003 per plant-year based on actual experience in pressurized water
reactors of two primary coolant leaks in 660 reactor years of operation.
Similarly, large leaks (area greater than 0.5~sq.~ft) were assigned a frequency
of 0.0001 per plant-year.

Given that a helium leak occurs, there is a very high likelihood ($>0.99$) that
the plant would be designed to reliably shutdown on low helium inventory, high
building radioactivity, or other protection trips.  Further, the plant would be
designed to continue forced cooling.  Depending on the leak size if time
permits it might be prudent to initiate an intentional helium depressurization
to lower the system pressure and the corresponding leak rate.  Either way the
circulators are designed to operate at the range of system pressures.  The
probability that forced cooling will also fail given that there is a helium
leak is taken from the Modular High Temperature Gas Cooled Reactor PRA as 0.1.
Therefore, the overall event frequency for small and large leaks coupled with a
loss of blanket cooling is $3\times 10^{-4}$ and $10^{-5}$ per plant-year,
respectively.

\subsection{Accident Source Terms}
\label{s-4-5-3}

The accident source terms were estimated by the ARIES/Starlite Team.  The
release of activation materials from the structure was estimated to be
negligible by examining the release of sodium nuclides, $^{22}$Na and
$^{24}$Na which are the dominant radio-nuclide as the temperature of the
first-wall and blanket structure is increased due to the afterheat during the
accident. Therefore, the major source of radioactivity during the accident is
the tritium.

There are two major sources of tritium.  First tritium exists to a small degree
in the coolant and in the purge gas as an impurity in the form of HT will be
present.  The amount is estimated as 1 to 5~g.  This evaluation assumed 3~g
available for release in seconds due to the blow-down.

Tritium is also produced in the beryllium multiplier at about one percent of
the rate in the lithium breeder.  Below 900~K the tritium will be retained in
the beryllium and be available for release during the event. If the event is
assumed prior to an annual heat-up to intentionally drive off and recover the
tritium, there is about 400~g that would be released following the loss of
blanket cooling in a time frame of 4 to 10~hours.  This analysis assumed all
400~g released in 8~hours.

The above HT releases from the above sources were assumed to be released
directly from the plant without retention or deposition in buildings.  Ground
level release was assumed.  A building wake factor was used corresponding to
building dimensions of 40 to 50~m high by 50~m wide and 100~m long.

An area of large uncertainty is the conversion of tritium, HT, in air to
tritiated water, HTO.  Based on experiments at Chalk River \cite{Bur88}] the
conversion in air is not rapid (only about 1.5\%/h), rather HTO forms in soils
from deposited HT followed by reemission into the air.  Thus, even after
passage of the plume the low rates of HTO to HT persist.  This is important
since the dose effectivity of inhaled HTO is four orders of magnitude greater
than for HT.

The meteorological data utilized was from a site used by EPRI on the advanced
light water reactor program.  The site encompassed 80\%-85\% of all US sites,
that is, only 15\%-20\% of US sites would have more adverse weather conditions
leading to higher off-site doses.  The site data used one year worth of
actual recorded data.  A realistic treatment of population movement was
employed and a realistic treatment of radionuclide settling from the building
to the site boundary was considered.

The ``best estimate'' releases from both the small and large leak loss of
cooling events were then statistically combined with the weather distribution
using a Monte Carlo code. \hbox{Figure~\ref{f-4-5-2}} provides pictorially how
the resulting dose distributions were combined and displayed as complementary
cumulative distribution functions for comparison with the EPA PAG requirement
at the plant boundary.

\begin{figure}[p]
\centerline{\psfig{file=sti-4-5-2.ps,width=6.25truein,clip=}}
\caption[f-4-5-2]
{Description of probability distribution functions as first step in cumulative
risk curve.}
\label{f-4-5-2}
\end{figure}

Figure~\ref{f-4-5-3} provides the preliminary \AIV hazard assessment results.
Two extremes are presented: one in which no tritiated water is formed and the
other in which all tritium is converted to the more dominant dose contributor
HTO.  As previously stated the expected result is much closer to the ``all HT''
curves so that for this class of events the PAGs are expected to be met with
significant margin.  However, the ``all HTO'' results point out the importance
of better understanding the conversion of HT to HTO.  Note that in this
abbreviated analysis only the uncertainty on the weather factored into the dose
calculations.  For example, the uncertainty in the source term was not
included.  Therefore, there is little sensitivity to the frequency of the two
leaks, in fact, there is little importance to whether the leak is small or
large.  Again more detailed realistic modeling of the holdup in the buildings
would likely decrease the small leak doses relative to those of the large leak.

\begin{figure}[b]
\centerline{\psfig{file=sti-4-5-3.ps,height=4.2truein,clip=}}
\caption[f-4-5-3]
{Preliminary ARIES-IV hazard assessment results compared to PAG
(Break in the ARIES-IV helium-coolant line).}
\label{f-4-5-3}
\end{figure}

If, after a more comprehensive assessment with more events and more
mechanistic consequence modeling is performed, greater margin is desired,
three areas of the design could be adjusted as discussed below:

\begin{enumerate}

\item
The accident source term could be reduced by more detailed quantification, by
heating the beryllium blanket more frequently, or by reducing the plant power
level;

\item
The likelihood of the accident could be reduced by minimizing the number of
coolant lines and/or their lengths, by providing welded versus bolted
penetration closures, or by increasing the reliability of the forced helium
cooling of the blanket;

\item
The accident releases could be reduced by providing filtered release from the
building, by providing elevated release ({\it i.e.,} a stack), by providing a
retentive containment building, or by providing a larger plant boundary.

\end{enumerate}

This preliminary hazard assessment selected primary coolant leaks and a loss of
forced cooling as a representative event class to demonstrate the method for
the \AIV design.  The study was not meant to definitely assess compliance with
the off-site dose requirement, but rather to get ``a feel for the lay of the
land.''  All indications are that a more comprehensive assessment would show
that compliance is achievable without major design changes or significant
technology development primarily because the source term is limited, there are
no internal sources of chemical energy, and the potential to instantaneously
transport the source term from the plant is very low.

\section{SUMMARY AND CONCLUSIONS}
\label{s-4-6}

The major conclusions of the Safety and Licensing tasks are: (1)~Review of NRC
documentation yielded important insights in the context of fusion power
systems; (2)~A Strawman Pathway was proposed for the development of fusion
regulatory policy and requirements; (3)~Top-level safety and licensing
requirements were established for fusion power systems; and (4)~A methodology
was established for demonstrating that sheltering and evacuation is not
required for fusion power systems.

\clearpage

\begin{thebibliography}{9}

\bibitem{Hof1}
G.~G. Hofer, ``NRC Jurisdiction of Fusion Power,'' Raytheon Nuclear
Inc. Report (May 1995).

\bibitem{Hof2} G.~G. Hofer, ``NRC Regulations and Fusion Power,'' Raytheon
Nuclear Inc. Report (May 1995).

\bibitem{Hof3}
G.~G. Hofer, ``NRC Licensing Process,'' Raytheon Nuclear
Inc. Report (May 1995).

\bibitem{Hof4}
G.~G. Hofer, ``NRC Tritium Requirements,'' Raytheon Nuclear
Inc. Report (May 1995).

\bibitem{EPA-520}
``Manual of Protective Action Guides and Protective Actions for
Nuclear Incidents,'' EPA Report \hbox{EPA-520/1-75-001}, Sept.~1975 (Revised
June 1980).

\bibitem{Mil87}
John Miller, Lawrence Livermore National Laboratory, private communications.

\bibitem{Bur88}
C.~D.~Burnham, R.~H.~Brown, G.~L.~Ogram, and F.~S.~Spencer, `` An Overview of
Experiments at Chalk River on HT Dispersion in the Environment,'' {\it
Proc. 3rd Topical Meeting of Tritium Technology in Fission, Fusion, and
Isotopic Applications,} (May 1988) Toronto, Canada, {\it Fusion
Technol.} {\bf 14} (1988) 1159.

\end{thebibliography}

\end{document}