\title{\bf 3. ECONOMICS AND COSTING}
\author{
\autlist{}{Ronald~L.~Miller}{}
}
\date{ }
\maketitle

\begin{titlepage}
{%\baselineskip=1.8ex
\tableofcontents
}
\end{titlepage}

\setcounter{chapter}{2}
\setcounter{page}{1}

\chapter{ECONOMICS AND COSTING}

\section{INTRODUCTION}
\label{s-3-1}
 
The multi-institutional Starlite Project~\cite{Wag95} is the initial phase of a
conceptual design of a demonstration (Demo) power plant, based on the tokamak
approach to magnetic fusion and strongly coupled to commercial considerations.
Together with public acceptance and regulatory simplicity, both deriving from
favorable safety and environmental performance, satisfactorily competitive
economics addresses a key Starlite requirement~\cite{Wag95,Kas94} and provides
an organizing nexus and object function for tokamak improvements.  Key economic
goals and requirements, as viewed by the power-producer community, are
updated~\cite{DeF78} in a broadened context of the fission
industry~\cite{EPRI90,Ton94}, as well as fusion-specific recommendations of a
Utility Advisory Committee~\cite{Wag95}.  Anticipation of future load growth,
coupled with timely and optimal capacity addition, is the classic
problem~\cite{Fis75} of traditional utilities or other evolving power-producer
entities, with societal penalties for both underbuilding or
overbuilding~\cite{IAEA84}.

Projections of future power plant costs are used in energy forecasting
models~\cite{Cla95} and, therefore, can influence public policy planning, which
can affect the allocation and priorities within the portfolio of energy R\&D
funds.  The R$\&$D phase represents the investment of time and resources to
develop information and expertise anticipated to facilitate the implementation
of the optimal Demo at reduced uncertainty ({\it i.e.,} risk).  While an
integrated global economic/environmental modeling effort is beyond the scope
of the Starlite Study, cooperation with such efforts~\cite{Cla95} can better
characterize the market penetration of fusion~\cite{Con90,Kaw93}, relative to
its suitably characterized competitors~\cite{Sta92}.  All identified
externalized adverse impacts of these technologies, as a matter of public
policy, should be explicitly internalized as mitigating operating costs or tax
disincentives~\cite{Jon90,Hob95}.  In so doing, the case for projecting the
successful Economics Demonstration element of the Starlite Mission~\cite{Wag95}
is established.

The timing of the introduction of fusion, subject to adjustment by the funding
pace and technical successes/failures of the R\&D effort~\cite{Kaw93}, is
calibrated here, but not conceptually restricted by, the most recent
U.S. comprehensive planning document~\cite{NES91}.  Following a ten-year
construction lead-time, initial operation of the Demo was targeted for
$\sim$2025, with the first commercial power plant (contingent upon a successful
Demo) targeted for initial operation $\sim$2040.

While it may be possible to characterize energy options in terms of energetics
and materials requirements~\cite{Han82} without explicit reference to the
corresponding economics, a cost based framework is useful and consistent with
systems engineering practice~\cite{Bla90,Neu90,DOE4700}.  Cost optimization
focuses the physics and engineering choices and trades made in the course of
the Starlite study.  Key cost drivers continue to be plant size, system power
density, recirculating power fraction, use of expensive/exotic
materials~\cite{Kra95,Kra95A}, with increased attention to operational
availability, as driven by unplanned and planned outages.  In contrast to Cost
of Electricity (COE) projections made historically for 10th-of-a-kind
commercial power plants, specific considerations for a first-of-a-kind (FOAK)
Demo include a possible longer construction lead time, the absence of
learning-curve credits~\cite{Arg90}, higher contingency costs~\cite{Del93}, and
special arrangements consistent with a Demo-specific utility-government
financial partnership to spread risk.  As these Demo-specific considerations
are worked out, a Demo cost summary can be derived from the corresponding
commercial summary as needed.

The remainder of this section describes certain aspects of the expression
defining the projected levelized Cost of Electricity in Sec.~\ref{s-3-2}.  The
role of the projected plant capacity factor is discussed in Sec.~\ref{s-3-3}.
A preliminary target space for future fusion market penetration is established
in Sec.~\ref{s-3-4}.  Conclusions of this reassessment of the Starlite costing
methodology and context are summarized in Sec.~\ref{s-3-5}.

\section{COST MODEL}
\label{s-3-2}

The present commercial power plant costing model~\cite{ARIESIV} provides a
point of departure for the Starlite study, as well as a opportunity to revisit
and re-calibrate all features, as found to be appropriate.  Development of the
power plant cost summary of Table~\ref{t-3-2-1} begins with the assessment of
the direct costs, organized by a comprehensive Cost Breakdown Structure
(CBS)~\cite{Del93,ARIESIV}, resolved into sufficient levels of detail to
adequately characterize the conceptual design.  Each Direct Cost entry may be
resolved into factory fabrication, site material, and site labor cost
components.  A suitable distinction between lower conventional unit costs and
higher so-called nuclear-safety-grade (``N-stamped") unit costs, consistent
with U.S.  Code of Federal Regulations 10CFR50, Appendix B, and updating the
application of Level of Safety Analysis (LSA) credits~\cite{ARIESIV} is made.

\begin{table}[p]
\caption{}
\centering{\bf Taxonomy of Fusion Demo Life-Cycle Costs}
\vspace{0.45cm}
{\small
\renewcommand{\arraystretch}{0.87}
\begin{tabular}{l @{\hspace{2.cm}} c}\hline
Cost Component \hfill&Type$^{(a)}$               \\
\hline \\
\quad R$\&$D Costs$^{(b)}$ & f  \cr
\quad Capital Costs:       &    \cr
\quad\quad Direct Costs$^{(c)}$ & f  \cr
\quad\quad\quad Land and land rights & \cr
\quad\quad\quad Structures and improvements & \cr
\quad\quad\quad Reactor Plant Equipment (RPE) & \cr
\quad\quad\quad\quad Reactor Equipment$^{(d)}$ & \cr
\quad\quad\quad\quad Main heat transfer system & \cr
\quad\quad\quad Turbine Plant Equipment (TPE) & \cr
\quad\quad\quad Electric Plant Equipment (EPE) & \cr
\quad\quad\quad Miscellaneous Plant Equipment & \cr
\quad\quad\quad Heat rejection system & \cr
\quad\quad Indirect Costs:      &    \cr
\quad\quad\quad Construction Services & f \cr
\quad\quad\quad Home Office Eng. $\&$ Serv. & f \cr
\quad\quad\quad Field Office Eng. $\&$ Serv. & f \cr
\quad\quad\quad Owner's Costs$^{(e)}$   & f  \cr
\quad\quad\quad Project Contingency$^{(f)}$     & f  \cr
\quad\quad\quad AFUDC$^{(g)}$           & f  \cr
\quad Production Costs:    &    \cr
\quad\quad Fuel (Deuterium)     & v  \cr
\quad\quad Scheduled Component Replacement & v  \cr
\quad\quad O$\&$M:              &    \cr
\quad\quad\quad Staff           & f,v\cr
\quad\quad\quad Coolant makeup  & v  \cr
\quad\quad\quad Breeder makeup  & v  \cr
\quad\quad\quad Other consumables & f,v\cr
\quad\quad\quad Waste disposal  & v \cr
\quad Decommissioning Costs& f  \cr
\\ \hline
\multicolumn{2}{l}{$(a)$ ``f'' denotes fixed cost, ``v'' denotes variable
cost.}\\
\multicolumn{2}{l}{$(b)$ Typically amortized or excluded as ``sunk"
 from commercial power plant cost estimates.}\\
\multicolumn{2}{l}{$(c)$ See Ref.~\cite{ARIESIV} for CBS details.}\\
\multicolumn{2}{l}{$(d)$ May contribute more than 50\% of the
direct cost.}\\
\multicolumn{2}{l}{$(e)$ The sum of Direct Costs and Indirect Costs
to this point yields the Base Cost.}\\
\multicolumn{2}{l}{$(f)$ Added to the Base Cost yields the Overnight
Cost.}\\
\multicolumn{2}{l}{$(g)$ Allowance for Funds Used During Construction,
 {\it i.e.,} interest paid on borrowed capital.}\\
\multicolumn{2}{l}{\phantom{$(g)$} Added
 to the Overnight Cost yields the Total Capital Cost (TCC), which dominates}\\
\multicolumn{2}{l}{\phantom{$(g)$}
 the Production and Decommissioning Costs.}\\
\end{tabular}
}
\label{t-3-2-1}
\end{table}

Cost components are distinguished as ``fixed" or ``variable" w.r.t. the plant
capacity factor, $p_{f}$ (see next section).  At the retail level, fixed costs
are associated with so-called demand charges and variable costs are associated
with energy charges.  At this phase of the Starlite study, cost items are
represented by parametric cost estimates and analogous cost estimates, rather
than direct engineering and vendor quotes, consistent with Fig. 17.8 of
Ref.~\cite{Bla90}.  To the extent that certain Balance of Plant (BOP) systems
({\it e.g.,} turbogenerators) are selected in common with existing plants,
firmer costs are available~\cite{Cro88,Del88}.  Costing of the tokamak Fusion
Power Core (FPC) benefits from recent ITER work~\cite{ITER95}.  Historical
costs have been brought up to a given reference year using the overall
U.S. Gross National Product implicit price deflator~\cite{Del95}, but will
henceforth be adjusted using more specific indices ({\it cf.} Table 84 of
Ref.~\cite{Edi94}).  Figure~\ref{sti-3-2-1} summarizes the various price
deflators of interest.  The reported indices are here normalized to a 1980 base
year with price deflator (PD) equal to unity.  Historic information and cost
projections dating back to 1965 can be brought forward to the reference year
for purposes of comparison.  The various indices show the period of relatively
high price inflation in the late 1970s in contrast with the more moderate
recent trend.  The Handy Whitman Index of Public Utility Construction
Costs~\cite{Del95} suggests a somewhat higher sector rate of recent price
increase than the general rate, although the North Atlantic (NA) and the
Pacific regions tend to outpace the nationally averaged index~\cite{Edi94}.
Absent recent, detailed, fusion-specific, vendor-provided, cost information,
estimates kept current using such PD factors are appropriate to the conceptual
level of the Starlite project.

\begin{figure}[t]
\centerline{\hspace*{2.cm}\psfig{file=sti-3-2-1.ps,height=4.2in,clip=}}
%\vspace*{1.5cm}
\caption[sti-3-2-1]
{Comparison of U.S. historic price deflator (PD) factors. The ARIES Systems
Code (ASC)~\cite{ARIESIV} uses an index linked to the Gross National Product
(GNP), until its discontinuance in 1990 and replacement by the Gross Domestic
Product (GDP).  The North Atlantic (NA) regional index tends to be larger than
the national average for both the GDP and the Handy Whitman (HW) sector Index
of Public Utility Construction Costs~\cite{Del95}.}
\label{sti-3-2-1}
\end{figure}

All costs are summed to yield the Total Direct Cost (TDC).  Indirect costs
are estimated using percentage factors~\cite{ARIESIV}.

The Cost of Electricity (COE) estimate at the busbar (neglecting transmission
and distribution cost components of the retail price) combines the total
cost estimate with reference economic ground-rules to yield
%
\begin{eqnarray}
\label{e-3-1}
COE & = &  \frac{C_{AC} + \left(C_{O\&M} + C_{SCR} + C_F\right) (1 + y)^Y}
  {(8.760E-3) \, P_E \, p_f}  \, + \, C_{D} \, + \, C_{R\&D} \: ,
\end{eqnarray}
%
where $C_{AC} (M\$)= TCC \times FCR$ is the annual capital cost and $P_{E}$
(MWe) is the net electrical output power, {\it i.e.,} the Design Electrical
Rating (DER).  While each term in the definition of COE may be considered
strictly to vary over the life of the plant, a convenient approximation is that
each term represents a time average.  The fixed values of decommissioning cost,
$C_{D}$, and R\&D cost, $C_{R\&D}$, are cast into (mill/kWeh) units.  The
general inflation rate is $y$ ({\it i.e.,} 0\%/yr for constant-dollar
evaluations and 5$\%/yr$ for nominal-dollar evaluations).  For a reference
construction spending profile~\cite{She86}, interest during construction
charges are calculated for the construction lead time, $\tau_{c}=Y$.
Projections of life-cycle costs as a figure of merit allow characterization of
the pre-Demo R\&D phase~\cite{Pos92,Joh94}, construction phase, operational
life, and end-of-life decommissioning phase~\cite{LaG86,Yankee94} of such a
project as a discriminator between candidate Demo designs~\cite{Bat95} and
various subsystem options.

Standard financial assumptions are invoked to facilitate comparisons with
competitive electrical generating technologies, although special financial
arrangements for a federal-government/power-producer partnership appropriate
for a fusion Demo are being identified.  Under one possible funding scenario,
The U.S. fusion Demo is envisioned as a joint venture between the Federal
government and a consortium of private interests~\cite{Cong83,S80}, with a
power purchase contract.  The Federal real discount rate under OMB Circular
A-94 is 10\%, close to that calculated for U.S. investor-owned utilities, such
that no proportional weighting is necessary~\cite{ARIESIV,Qui91}.  High
discount rates tend to minimize long-term benefits and discourage capital
intensive projects.  The discount rate is an important issue in discussions of
intergenerational equity bearing on energy policy and resource depletion, as
well as in international differences in the evaluation of cost-benefit ratios.
Considerations relating to the Demo as a first of a kind (FOAK) device with
appropriately higher-than-commercial contingency cost~\cite{Del93} and the
narrow scaling step~\cite{Wag95} between the Demo and subsequent commercial
fusion power plants are monitored.  The tokamak Demo could well be built to the
same physical specifications as the anticipated commercial power plant and
operated at lower power by operating the coils at a slightly derated field
strength.

Considerations of the spinning reserve requirement of the grid tend to inhibit
very large single plants, with the contemporary ``rule of thumb" limiting the
addition to $\sim$7\% of the grid; future load growth and greater
interconnectivity may be anticipated to relax this constraint.  Economies of
scale, it is argued~\cite{Log93,Dol93}, suggest the choice of very large fusion
power plants to reduce the COE.  Projections that have been used to support
this view have tended to assume a fixed plant capacity factor, resulting in
\hbox{$COE \propto P_{E}^{-0.6}$}, but neglecting the increasingly adverse
impact of higher neutron wall load with fixed fluence lifetime on operation
time.

The unit will tend to be limited by the largest single turbogenerator unit
(with gross electrical power output presently $\sim$1,350~MWe in the
U.S. (60~Hz at 1,800~rpm) and $\sim$1,500~MWe in France (50~Hz at 1,500~rpm).
Because of the generally larger recirculating power requirements for tokamak
fusion (because of plasma current drive) relative to fission, the net power
output of the fusion unit would be correspondingly lower.  A false
counterexample to this view is the recent British Sizewell-B PWR, which has two
650-MWe class turbogenerators, representing the largest conveniently available
domestic component while not linking the introduction of first British PWR to a
new BOP technology.  The corresponding use of two turbines in a fusion plant
could allow a single $\sim$2,400~MWe(net) plant (U.S.) or $\sim$2,800~MWe(net)
plant (France) at a modest additional cost counteracting the economy of scale.
It is rather recommended to consider multiple units of the largest
single-turbogenerator size at suitable sites, consistent with fission and coal
experience. Some savings due to shared staff and support facilities can be
realized.

Once a COE for a given plant size is determined, it is not recommended to
re-scale the COE to a different output for comparison purposes ({\it e.g.,} 
as done in Ref.~\cite{Del94}), particularly if the scaling exponent is set
arbitrarily (rather than consistent with the design study itself) and the
scaled design violates some constraint applied in the original design.

\section{PLANT CAPACITY FACTOR}
\label{s-3-3}

The plant capacity factor, $p_{f}$, is the ratio of the energy actually
generated in a reference time period to the energy that would have been
generated in that time period had the plant been operating full time at its
Design Electrical Rating (DER).  As a figure of merit, $p_{f}$, captures the
plant operational availability, $ A$, in terms of scheduled (planned) and
unscheduled (forced) outages, as corrected for startup and shutdown transients
and any load-following operation.  A projection of $A$ for a future power-plant
technology is necessarily very uncertain, but an allocation of target outage
times, as summarized in Table~\ref{t-3-3-1}, sets goals and requirements for
the Reliability, Availability, and Maintenance (RAM) activity of the conceptual
Demo design.  Itemized $A_{i}$ values for each system reflect Mean Time to
Failure (MTTF) and Mean Time to Repair/Replace (MTTR) estimates.

\begin{table}[b]
\caption{}
\centering{\bf Preliminary Availability Allocation}
\vspace{1.0cm}
\renewcommand{\arraystretch}{1.1}
\begin{tabular}{l @{\hspace*{1.in}} c}
\hline \\
Scheduled down-time, $T_{S} (day/yr)$   & 22.5$^{(a)}$ \cr
Unscheduled down-time, $T_{U} (day/yr)$ & 25.0 \cr
Operation time, $T_{O} (day/yr)$       & 317.5 \cr
Forced outage rate, $FOR^{(b)}$        &0.075 \cr
Operational Availability, $A^{(c)}$:   &  \cr
\quad Early operation                  & $\ge$0.30 \cr
\quad Mature operation                 & 0.87 \cr
Plant capacity factor, $p_{f} \propto A$: & \cr
\quad Early operation                  & $\ge$0.25 \cr
\quad Mature operation$^{(d)}$         & 0.75-0.80 \cr
\\ \hline
\multicolumn{2}{l}{ $(a)$ Consistent with 30 days/outage at routine 18-month intervals}\\
\multicolumn{2}{l}{\phantom{$^(a)$} and an extended 45 day
outage each decade for turbine overhaul, {\it etc.}.}\\
\multicolumn{2}{l}{$(b)$ $FOR \equiv T_{U}/(T_{O}+T_{U})$}\\
\multicolumn{2}{l}{$(c)$ $A \equiv (1 - FOR) (365-T_{S})/365$}\\
\multicolumn{2}{l}{$(d)$ Used in COE projections.}\\
\end{tabular}
\label{t-3-3-1}
\end{table}

\section{MARKET CONTEXT}
\label{s-3-4}

The results of Ref.~\cite{Del94} are generalized in Fig.~\ref{sti-3-4-1} to set
the market context for electrical production in the $\sim$2025 time frame for
Demo and the $\sim$2040 time frame for early commercial fusion power plants.
Included are constant-dollar busbar Cost of Electricity [COE (mill/kWeh)]
projections for fission, including an evolutionary light water reactor (ELWR)
and a passively-safe advanced light water reactor (ALWR), an advanced
pulverized-coal (PC) plant, and a combined cycle combustion turbine (CCCT)
burning natural gas.  The fission cost projections assume a favorable
regulatory and licensing climate and a solution to the radioactive waste
disposal issue, absent which, no additional fission capacity is
likely~\cite{EIA94,EIA95,EIA96}.  The coal and natural gas projections,
neglecting regional variations, are shown for a range of fuel-cost escalation
rates over and above the general inflation rate (5\%/yr), consistent with
eventual depletion.  The near-term picture favors the use of natural gas,
particularly in small units as the lowest cost option for incremental capacity,
although displacement by coal is projected~\cite{EIA95} after $\sim2010$.  Near
term natural gas costs were thought to be growing at a rate nearer to the
2\%/yr curve~\cite{EIA94,EIA95}, but the most recent~\cite{EIA96} data and
extrapolations suggest less growth and even a decline in price.  The situation
for coal is similar if less dramatic, as shown in Fig.~\ref{sti-3-4-2}.  Of
course, these long range projections are uncertain and must be used cautiously.

\begin{figure}[p]
\centerline{\hspace*{2.cm}\psfig{file=sti-3-4-1.ps,height=5.8in,clip=}}
%\vspace*{3.0cm}
\caption[sti-3-4-1]
{Busbar Cost of Electricity [COE (mill/kWeh)] projections for future
competitive technologies to fusion, setting the market penetration context,
based on Ref.~\cite{Del94}.  The fission projections are for an evolutionary
light water reactor (ELWR) and a passively-safe advanced light water reactor
(ALWR)~\cite{EPRI90,Del94}.  The coal and natural gas [combined cycle
combustion turbine (CCCT)] projections are shown for a range of fuel cost
escalations.  The assumed plant capacity factor, $p_{f}$, is also an aggressive
target for fusion power plants.  Target windows for the Starlite Demo and
subsequent commercial power plants ({\it e.g.,} tenth-of-a-kind \hbox{ARIES-IV}
tokamak~\cite{ARIESIV} with indicated six-year construction lead time) are
indicated by the dashed boxes.}
\label{sti-3-4-1}
\end{figure}

\begin{figure}[t]
\centerline{\hspace*{2.cm}\psfig{file=sti-3-4-2.ps,height=4.8in,clip=}}
%\vspace*{3.0cm}
\caption[sti-3-4-2]
{Fuel cost projections for natural gas (NG) and coal from a series of recent
U.S. Energy Information Agency (EIA) estimates for 1994 ~\cite{EIA94} (open
circles), 1995~\cite{EIA95} (partially filled circles), and 1996~\cite{EIA96}
(filled circles) indicating the softening of these fossil-fuel prices.  The
extrapolation curves~\cite{Del94} for the indicated assumed escalation rates
are more consistent with then-available projections.  A fission fuel
point~\cite{Del88} is included for comparison.}
\label{sti-3-4-2}
\end{figure}

Resolution of the COE into its fixed and variable cost components allows
comparison of the fusion estimate with those of potential competitors {\it
calculated on the same basis} in the context of the Load Duration Curve, a
standard electrical planning device, as illustrated in Fig.~\ref{sti-3-4-3}.
The horizontal axis of the LDC frame denotes the number of hours per year that
the given load, normalized by a typical 15--20~GWe, would be exceeded.
Selected non-fusion cases from Table~6 of Ref.~\cite{Del94} are compared with
the preliminary reverse-shear Starlite Demo candidate of Ref.~\cite{Bat95}.
Capital intensive plants, ranked by the $p_{f}=0$ vertical-axis intercepts,
with high plant capacity factors provide base-load operation.  Plants with high
production costs (proportional to the slope of the screening curves) are used
to address peak loads.  The early operational behavior of the fusion Demo,
characterized by intermittent operation in a reliability growth phase, may lend
itself to dispatching for peak loads and will depress its lifetime-average
$p_{f}$.  Mature Demo performance would be $p_{f} \simeq 0.80$, consistent with
the availability goal of \hbox{$A \simeq 0.87$}~\cite{Wag95}.

\begin{figure}[p]
\centerline{\hspace*{1cm}\psfig{file=sti-3-4-3A.ps,width=10.5truecm,clip=}}
\vskip 0.3truecm
\centerline{\hspace*{1.cm}\psfig{file=sti-3-4-3B.ps,width=10.5truecm,clip=}}
\caption[sti-3-4-3]
{Screening curve representation of COE values (upper frame), resolved into
fixed ($\propto$ vertical-axis intercept) and variable ($\propto$ slope)
components, linked to a representative annual (8760 hour) Load Duration Curve
(lower frame)~\cite{IAEA84}.  Crossings of the screening curves suggest the
allocation of the various plant types on the grid in response to the diurnal
and seasonal variations of load to minimize system costs.}
\label{sti-3-4-3}
\end{figure}

\begin{figure}[t]
\centerline{\hspace*{2.cm}\psfig{file=sti-3-4-4.ps,height=4.2in,clip=}}
\caption[sti-3-4-4]
{Fusion power plant design window in terms of unit overnight cost,
UOC $(\$/kWe)$, and plant capacity factor, $p_{f}$, leading to
projected constant-dollar busbar Cost of Electricity, COE (mill/kWeh).}
\label{sti-3-4-4}
\end{figure}

The cost-based design window for the Demo and subsequent commercial fusion
power plants is illustrated in Fig.~\ref{sti-3-4-4}.  The unit overnight cost
includes direct costs plus indirect costs plus contingency costs.  The Total
Capital Cost is then the sum of the Overnight Cost and the interest cost during
construction.  The portion of the total COE allocated for Production Costs
[{\it i.e.,} fuel (negligible for fusion), non-fuel O$\&$M, and scheduled
component replacement (SCR)] plus decommissioning is taken to be a typical
\hbox{COE$^{*} \simeq 13$~mill/kWeh}.  In this context that the
Starlite~\cite{Wag95} Goals [80~mill/kWeh (Demo), 65~mill/kWeh
(Commercial)] and Requirements [90~mill/kWeh (Demo), 80~mill/kWeh (Commercial)]
can be resolved into major components.

\section{SUMMARY AND CONCLUSIONS}
\label{s-3-5}

The economic methodology to be used in the Starlite tokamak fusion Demo study
has been determined in advance of the integration of the physics and
engineering into a detailed reference design.  Cost considerations are used
within the project in an iterative manner to guide the design process toward an
optimal tokamak Demo as reported results interface with the external world of
energy forecasting and policy determination, with implications for the planning
of the magnetic fusion R$\&$D program.  A coherent linkage between the Demo and
the subsequent commercial tokamak power plant is established in response to the
present perception of future energy market requirements and goals.  As the
Starlite Project progresses, exposition of cost information anticipates the
concerns of future Demo participants and addresses formal documentation and
traceability considerations~\cite{DOE5700}.

\clearpage

\begin{thebibliography}{99}
 
\bibitem{Wag95} L.~Waganer, F.~Najmabadi, M.~S.~Tillack, and the ARIES
Team, ``What Must Demo Do?''\IEEE{16} 1157.

\bibitem{Kas94} J.~Kaslow, \ea, ``Criteria for Practical Fusion Power
Systems - Report from the EPRI Fusion Panel,'' Electric Power Research
Institute report BR-104469 (1994).

\bibitem{DeF78} D.~A.~DeFreece, ``Fusion Energy: Utility Requirements and
Economics,'' {\it Fusion Reactor Design Concepts,} International Atomic Agency,
IAEA-TC-145/48 (1978).

\bibitem{EPRI90} ``Advanced Light Water Reactor - Utility Requirements
Document,'' Electric Power Research Institute report NP-6780 (March 1990).

\bibitem{Ton94} L.~S.~Tong, ``Adoption of New Design Features for the Next
Generation Nuclear Power Reactors,''
{\it Nuclear Safety,} {\bf 35} (1994) 98.

\bibitem{Fis75} R.~Fischl, ``Optimal System Expansion: A Critical Review,''
{\it Systems Engineering for Power: Status and Prospects}, in Proc. an
Engineering Foundation Conf. sponsored by the U.S. Energy Research \&
Development Administration and Electric Power Research Institute, CONF-750867
(August 1975) 233.

\bibitem{IAEA84} ``Expansion Planning for Electrical Generating Systems,''
International Atomic Energy Agency Technical Reports Series No. 241 (1984).

\bibitem{Cla95} J.~Clarke, ``Environmental Issues and Global Energy Economy
 Project,'' \IEEE{16}.

\bibitem{Con90} R.~W.~Conn \ea, ``Economic, Safety and Environmental Prospects
of Fusion Reactors,'' {\it Nucl. Fusion,} {\bf 30} (1990) 1919.

\bibitem{Kaw93} P.~K.~Kaw, ``Fusion Power: Who Needs It?'' \IAEA{14} (1993) 3.

\bibitem{Sta92} C.~Starr, M.~F.~Searl, and S.~Alpert, ``Energy Sources: A
Realistic Outlook,'' {\it Science,} {\bf 256} (15 May 1992) 981.

\bibitem{Jon90} P.~M.~S.~Jones, ``Social Costs of Energy,'' {\it Atom,} {\bf
403} (1990) 23.

\bibitem{Hob95} B.~F.~Hobbs and P.~Centolella, ``Environmental Policies and
Their Effects on Utility Planning and Operations,'' {\it Energy,} {\bf 20}
(1995) 255.

\bibitem{NES91} {\it National Energy Strategy - Powerful Ideas for America},
First Edition 1991/1992, U.S.\ Department of Energy report (Feb. 1991).

\bibitem{Han82} B.~Hannon, ``Energy Discounting,'' {\it Technology Forecasting
\& Social Change,} {\bf 21} (1982) 281.

\bibitem{Bla90} B.~S.~Blanchard and W.~J.~Fabrycky, {\it Systems Engineering
and Analysis,} Prentice Hall (1990).

\bibitem{Neu90} R.~de~Neufville, {\it Applied Systems Analysis,}
McGraw-Hill, Inc. (1990).

\bibitem{DOE4700} {\it Department of Energy Project Management System},
U.S.\ Department of Energy Draft Order DOE 4700.1A (10 Mar. 1995).

\bibitem{Kra95} R.~A.~Krakowski, ``Simplified Fusion Power Plant Costing: A
General Prognosis and Call for `New Think','' {\it Fusion Technol.,}
{\bf 27} (1995) 135.

\bibitem{Kra95A} R.~A.~Krakowski, ``Magnetic Fusion Reactor Economics,''
\IEEE{16} 1549.

\bibitem{Arg90} L.~Argote and D.~Epple, ``Learning Curves in Manufacturing,''
{\it Science,} {\bf 247}  (23 Feb. 1990) 920.

\bibitem{Del93} J.~G.~Delene and C. R. Hudson II, ``Cost Estimate Guidelines
for Advanced Nuclear Power Technologies,'' Oak Ridge National
Laboratory report ORNL/TM-10071/R3 (May 1993).

\bibitem{ARIESIV} \ARIESIV.

\bibitem{Cro88} J.~H.~Crowley \ea, ``Technical Reference Book for the Energy
Economic Data Base Program EEDB Phase IX (1987),'' U.S.\ Department of Energy
report DOE/NE-0092 (July 1988).

\bibitem{Del88} J.~G.~Delene, K. A. Williams, and B. H. Shapiro, ``Nuclear
Energy Cost Data Base,'' U.S.\ Department of Energy report DOE/NE-0095
(Sept. 1988).

\bibitem{ITER95} {\it ITER Interim Design Report} (12 July 1995).

\bibitem{Del95} J.~G.~Delene, Oak Ridge National Laboratory, personal
communication (24 Oct. 1995).

\bibitem{Edi94} Edison Electric Institute, ``Statistical Yearbook of the
Electric Power Industry 1993,'' (1994) p.~96.

\bibitem{She86} J.~Sheffield \ea, ``Cost Assessment of a Generic Magnetic
Fusion Reactor,'' {\it Fusion Technol.,} {\bf 9} (1986) 199.

\bibitem{Pos92} M.~J.~M.~Posner and D.~Zuckerman, ``A Note on Socially Optimal
R$\&$D Programs and Their Inducement,'' {\it Oper. Res.,}
{\bf 40}, Suppl. No. 2 (1992) S335.

\bibitem{Joh94} B.~E.~Johnson, ``Modeling Energy Technology Choices,''
{\it Energy Policy,} {\bf 22} (1994) 877.

\bibitem{LaG86} T.~S.~LaGuardia, ``Guidelines for Producing Commercial Nuclear
Power Plant Decommissioning Cost Estimates,'' {\it Proc.
American Power Conference,} {\bf 48} (1986) 964.

\bibitem{Yankee94} ``Yankee Rowe - Decommissioning Will Cost an Extra $\$$94
Million,'' {\it Nuclear News,} {\bf 37} (Dec. 1994) 23.

\bibitem{Bat95} C.~G.~Bathke and the ARIES Team, ``A Preliminary Systems
Assessment of the Starlite Demo Candidates,'' \IEEE{16} 1139.

\bibitem{Cong83} ``Alternative Financing Plan for the Clinch River Breeder
Reactor Project,'' Hearing before the Subcommittee on Energy Research and
Production of the Committee on Science and Technology, U.S.\ House of
Representatives (15 Sept. 1983).

\bibitem{S80} The System 80+ Team, ``Program Plan for Deployment of a System
80+ Multi-Purpose Nuclear Facility at Savannah River Site,'' (31 Mar. 1994).

\bibitem{Qui91} J.~Quirk and K.~Terasawa, ``Choosing a Government Discount
Rate: An Alternative Approach,'' {\it J.\ Environmental Economics and
Management,} {\bf 20} (1991) 16.

\bibitem{Log93} B.~G.~Logan, ``On the Utility of Tokamaks for Energy,''
{\it Fusion Eng. \& Des.,} {\bf 22} (1993) 145.

\bibitem{Dol93} T.~J.~Dolan, ``Fusion Power Economy of Scale,''
{\it Fusion Technol.,} {\bf 24} (1993) 97.

\bibitem{Del94} J.~G.~Delene, ``Advanced Fission and Fossil Plant Economics -
Implications for Fusion,'' {\it Fusion Technol.,} {\bf 26} (1994) 1105.

\bibitem{EIA94} Energy Information Administration, ``Annual Energy Outlook
1994,'' U.S.\ Department of Energy report DOE/EIA-0383(94) (Jan. 1994).

\bibitem{EIA95} Energy Information Administration, ``Annual Energy Outlook
1995,'' U.S.\ Department of Energy report DOE/EIA-0383(95) (Jan. 1995).

\bibitem{EIA96} Energy Information Administration, ``Annual Energy Outlook
1996,'' U.S.\ Department of Energy report DOE/EIA-0383(96) (Jan. 1996).

\bibitem{DOE5700} {\it Cost Estimating, Analysis, and Standardization},
U.S.\ Department of Energy Order DOE 5700.2D (12 June 1992).

\end{thebibliography}