PPT Slide
- Three TF return shells weigh 2.69 x 106 kg total
- Shells will be fabricated on site
- Costs includes process hardware and energy costs
- Fabrication is entirely computer directed
- Parts can be completed in six months (normal shifts)
- Cost is 10th of a kind, 1998$
Material Cost = $5.33 M (Includes waste)
Labor Cost = $0.31 M (Includes off-site rates)
Energy Cost = $0.04 M
Process Hwdr = $4.03 M (Vendor quotes)
Contingency = $1.94 M
Fees = $1.40 M
Total Cost = $13.05 M
Unit Cost = $4.85/kg
3. TF Return Shell Cost Development