FPN09-61
ITER Update
December 6, 2009
ITER, a joint venture among the U.S., EU, Russia, Japan, China, Korea
and India, is designed to produce 500 Megawatts fusion power using only
50 Megawatts to heat the plasma. Construction at the site in Cadarache,
France, is well underway. Thirty-nine buildings are being built. The
original construction cost estimate, made in 2001, of approximately 5.4
billion Euros, and the construction schedule, is under review and will
be considered at an interim ITER Council meeting probably in March,
with final approval of cost and schedule in June. Currently, first
plasma is scheduled for 2018. The original cost estimate did not
provide necessary funds for many items now considered necessary,
including finishing the design, developing infrastructure and various
support services. The cost of ITER construction is being born
approximately 45% by the EU and 9% by each of the other six parties.
There are currently approximately 440 people from the various parties
working at the site. Another 400-500 people are working on ITER in the
parties' ITER Domestic Agencies. ITER components are being built in the
various countries and are being contributed to ITER as "contributions
in kind." Currently, the ITER Organization has signed 28 Procurement
Arrangements with the various Domestic Agencies, with a total value
estimated at approximately 20% of the total ITER cost. Taking into
account the site-specific work now underway, approximately one-third of
the total ITER value is now under contract. A new set of Project
Specifications were approved in June 2008 and an Integrated Project
Schedule and Cost Estimate are being prepared by the ITER Organization
for the March interim ITER Council meeting. Items on the construction
critical path include the buildings, toroidal magnet coils and vacuum
vessel.
The U.S. contributions include the following ITER subsystems: Cooling
Water, Pellet Injector, Port-based Diagnostics, Toroidal Field
Conductor, Central Solenoid Windings, Blanket/Shield, In-vessel
Coils Design and R&D, Electric Power Systems Components,
ICH Transmission Lines and ECH Transmission Lines. Contracts totaling
$33 M have been awarded for TF Conductor, R&D and design have been
completed for CS Winding, Blanket/Shield has been redesigned and
fabrication methods are being investigated, contract award expected
soon for Cooling Water System, progress on all other U.S. obligations.
Talks on the status of ITER were given by Norbert Holtcamp, ITER
Principal Deputy Director General and by Ned Sauthoff, head of the U.S.
ITER Domestic Agency at Fusion Power Associates Annual Meeting and
Symposium, Dec 2-3 in Washington, DC. The talks are posted and can be
accessed at
http://fusionpower.org
and click on Annual Meetings and
Symposia , or at
http://fire.pppl.gov/fpa_annual_meet.html
Detailed
information on ITER, as well as links to the Domestic Agencies, is
available from the international ITER site:
http://www.iter.org