Based on the $5 billion ($FY2002) estimated cost provided by the ITER Project, the original U. S. estimate was $513 million. Using estimates obtained, in part, subsequently from U. S. industry, the U. S. revised that estimate upwards to $792 million, including an estimated $101 million for operation of the U. S. ITER Project Office. The U. S. estimate further added $132 million in contingency, bringing the total U.S. estimate to $924 million ($FY 2002). Including escalation during construction adds another $198 million, bringing the current estimated total cost to the U. S. to $1.122 billion (as spent dollars).
Although it has sometimes been said that ITER construction cost would be spread over 10 years, the DOE says this amount would be required over 8 years as follows:
FY 2006 $ 49.5 M
FY 2007 $146.0 M
FY 2008 $200.8 M
FY 2009 $207.5 M
FY 2010 $199.3 M
FY 2011 $160.3 M
FY 2012 $126.2 M
FY 2013 $ 32.4 M